TCN begins reconstruction of collapsed 330kV transmission towers in Kebbi

The Transmission Company of Nigeria (TCN) has commenced the reconstruction of three collapsed towers along the 330kV Kainji–Birnin Kebbi transmission line, which caused a major power outage across parts of Kebbi and Kaduna States.
In a statement issued on Saturday by the General Manager, Public Affairs, Ndidi Mbah, TCN disclosed that three separate contractors have been deployed to the site, with each assigned to rebuild one of the towers. This strategy, the company said, is aimed at accelerating repairs and ensuring the prompt restoration of power transmission in the affected areas.
“To mitigate the impact of the outage on Kaduna Electric and its customers, alternative supply routes have been activated,” Mbah said, noting that Sokoto and Birnin Kebbi are currently receiving 6MW to 7MW of bulk power via an alternative 132kV line routed through Mando-Zaria-Funtua-Gusau-Talata Mafara-Sokoto-Birnin Kebbi.
The company assured residents of its commitment to restoring full power as swiftly as possible, thanking communities for their patience during the repairs. “We regret the inconvenience caused and remain committed to the integrity and reliability of Nigeria’s power transmission infrastructure,” Mbah added.
The power outage began on Thursday, May 8, 2025, after the 330kV Kainji–Birnin Kebbi transmission line tripped, disrupting supply across the region. Kaduna Electric confirmed the incident in a statement by its Head of Corporate Communication, Abdulaziz Abdullahi, explaining that the disruption was caused by the collapse of three towers near Yauri town.
“The TCN team is working diligently to rectify the issue,” the company assured. “Normal power supply will be restored as soon as possible. We sincerely apologise for any inconvenience.”